Download Stand Establishment Info. Sheet

List of Treatments by Installation

Annual Field Work Schedules

Long-term Schedules for Field Work New!!

  • Type 1- Thinned Natural Stands
  • Type 2- Variable Density Plantations
  • Type 3- Red alder/Douglas-fir Species Mixtures

Estimated Crew Worker Days per Activity

Crew Worker Days Required for HSC Activities
Type 2 Activities Workers Days Crew Worker Days
Regen Survey 1 (1) 2 2
Plot Installation 1 (1) 2 2
3rd yr Measurement 5 (1) 2 10
Thin and Measurement 5 (1) 2 10
Prune 2 (1) 2 4
6th yr Measurement 5 (1) 3 15
9th yr Measurement 5 (1) 4 20
  (1) HSC RA 0 (1) HSC RA not included
in crew worker days estimate
Type 1 Activities Workers   Days   Crew Worker Days
Measurement 2 (1) 3 6
  (1) HSC RA   (1) HSC RA not included
in crew worker days estimate
Type 3 Activities Workers Days Crew Worker Days
Regen Survey 1 (1) 2 2
Plot Installation 1 (1) 1 1
Measurement 2 (1) 2 4
  (1) HSC RA   (1) HSC RA not included
in crew worker days estimate
*Estimates assume moderate terrain. For difficult terrain add 1 day per activity.